List of projects in Perm region

Talitsky area of the Verkhnekamsk potassium-magnesium salt deposit

Work places: 2300 by the time of plant launch

Productivity: 8 Mtpa
Talitsky mining and processing plant
1. Desinger;
2. EPCM contractor;
3. Consultant.
2. EPCM contractor;
3. Consultant.
According to the condition of license agreement of the Talitsky area development of the Verkhnekamsk potassium-magnesium salt deposit:
- comissioning time of mining enterprise – not later than 2021;
- due date of enterprise design capacity achievement – not later than 2023.