Home About us TOMS- project PLC (Kazakhstan)

 

 

TOMS- project PLC

 

 

The company was established in 2010.

The office is located at the following address: 

100019 Republic of Kazakhstan, Karaganda, Ermekova str., 29, office 405.

Yury Stolbchenko is the CEO.

 

 

Provided services:

Elaboration of project documentation at all stages: FS, Design criteria, project documentation and detail engineering.

Design objects:

  • Mining and processing facilities;
  • Open pits and subsurface mines;
  • Processing plants;
  • Mining and mixed production;
  • Hydro- technical utilities;
  • Infrastructure objects.

 

List of largest performed projects:

 

Altyntau Kokshetau PLC (Vasilkovsky mining and processing plant)

Gold ore mine development, open-pit mining, productivity 8 Mtpa. Functions of planner (Working project) – 2008.

Vasilkovsky mining and processing plant

Crushing  facility at Vasilkovsky mining and processing plant

 

Syrymbet JSC, Syrymbet mining plant

Elaboration of Design Specifications and Estimates for construction of mining and metallurgical enterprise specializing in tin ore extraction, productivity 1 Mtpa. Functions of planner.

Design objects:

  • Processing plant;
  • Tail facility;
  • Hydrometallurgical workshop.

 

EuroChem Fertilizers PLC

Development of Kok-Djon phosphate ore deposit (Araltobe, Kesiktobe) and Gimmelfarbskoye. Functions of general planner.

Design objects:

  • Quarry;
  • Infrastructure objects.

 

Varvarinskoye JSC

Reconstruction of gold recovery and processing plant (project documentation and detail engineering). Functions of General planner.

Design objects:

  • Unit of pre-leaching;
  • Unit of scavenger flotation.

 Recovery plant at Varvarinskoye deposit

Kazakhmys PLC

Dewatering of Abyz quarry. Functions of general planner.

Design objects:

  • Dewatering wells;
  • Water conduit.